Plumbing Project Information

We can hear it in our classroom (lucky us).
The great news is that when we return on August 9, 2007, this project will be completed.
May 21
Demolition of Boys Restroom, faculty room closet, principal's office restroom and kitchen closets.
May 23
Plumbers start work.
May 29
Excavation for water main in lower playground.
June 4
Start demolition of Girls Restroom, top floor janitor sink, 3rd grade classroom sink, hallway drinking fountains, watermain.
June 13
Plumbers work in all different areas.
July 2-6
Install piping.
July 9
Start patching, painting, tiling. Finish plumbing and water.
July 16
Trim plumbing valves.
July 23
Cleanup starts.
July 30
Punch list items and finish clean up.
Plumbing inspection to be scheduled at finish.